We wanted to provide the Township with an update regarding our Lake Redman Pumping Station project.

 

Our pumping station construction contractor, Wickersham Construction, has completed clearing the pumping station site, including the access drive alignment from South George Street.  They intend to begin rough-grading the driveway this week.  Their contract calls for work to be complete by the end of July 2017.

 

We have lowered the Lake Redman reservoir to facilitate construction.  The pool is currently down about 7 feet below the normal elevation.

 

Kinsley Construction will be installing the force main piping from the pumping station site to our Filter Plant on Grantley Road.  They will begin installing pipe in the overland area south of Joppa Road, and along Joppa Road north of Leader Heights Road, this week.

 

Please feel free to contact us if you have any questions.

 

Thanks,   Mark

 

Mark S. Snyder, P.E.

Vice President – Engineering
The York Water Company
130 E. Market St.
York, PA 17401

E: marks@yorkwater.com
D: (717) 718-2977
F: (717) 843-2715
www.yorkwater.com
NASDAQ: YORW